Client : | Balfour Beatty Construction | Value : | £4.2m | Location : | Tower Hill London | Time : | 58 Weeks |
- Basement Construction, drainage and waterproofing
- Connection to London Underground – Tower Hill Tube Station
- Construction of 3 in-situ concrete cores using both slip-form, jump-form and traditional techniques
- Suspended In-situ Ground Floor Slab
- Pre-cast Staircase and In-situ Landing installation
- Concrete to metal decking