Commercial

Siemen’s Blade Factory

This Regional Distribution Centre comprised of works including the foundations, drainage, services, external concrete service yard circa 50000m2. Plus drainage installation through difficult ground conditions being rock, attenuation tanks, external works and concrete service yards.

Client : Volker Fitzpatrick
Value : £4.5m
Location : Hull
Time : 1 Year

  • Circa 6000 pre-cast piles cropped
  • Pile cap and ground beam installation
  • Drainage, external yard slabs
  • 100m paint booth trenches