Commercial

Majestic Building

Installation of new raft foundations and retaining walls to a Grade 3 waterproof standard. Confined space working within one of Leeds most iconic listed buildings.

Client : Sir Robert McAlpines
Value : £2.9m
Location : Leeds
Time : 3 Years

  • Installation of new raft foundations and retaining walls to a grade 3 waterproof standard. Confined space working within one of Leeds most iconic listed buildings
  • 1400m2 waterproof raft slabs
  • 155m shotcrete retaining walls
  • 7 story slip form core
  • New internal drainage
  • Concrete to upper floors
  • All form work Provided by Leeds Acro
  • Restricted access working with confines of an existing building. Plant lowered into basement by hoist
  • 2000m3 material excavated from basement and removed using conveyor systems
  • Raft foundation works including core base construction
  • Slipform Core

Excellent commitment to safety

The Moortown Group has an excellent commitment to safety, delivered in line with our own Build Sure Commitments and your staff have shown familiarity with quality requirements.

Mark Gibson

Mark Gibson

Regional MD North East and Yorkshire, Sir Robert McAlpine.