Located on the Newcastle Helix Science Park Development.
Client : | Sir Robert McAlpine | Value : | £4.5m | Location : | Newcastle | Time : | 3 Years |
- Substructure works and Slip Formed Core – Construction Period 18 weeks
- 1200m2 concrete slabs and associated ground beams and pile caps
- 70m Concrete retaining walls
- Grade 2 waterproof structure
- 12 story slip form dual core
- Precast stair installation
- New internal and external drainage
- Concrete to 13 upper floors – 1400m2 over 9 weeks