Education

The Spark, Newcastle

Located on the Newcastle Helix Science Park Development.

Client : Sir Robert McAlpine
Value : £4.5m
Location : Newcastle
Time : 3 Years

  • Substructure works and Slip Formed Core – Construction Period 18 weeks
  • 1200m2 concrete slabs and associated ground beams and pile caps
  • 70m Concrete retaining walls
  • Grade 2 waterproof structure
  • 12 story slip form dual core
  • Precast stair installation
  • New internal and external drainage
  • Concrete to 13 upper floors – 1400m2 over 9 weeks

Excellent commitment to safety

The Moortown Group has an excellent commitment to safety, delivered in line with our own Build Sure Commitments and your staff have shown familiarity with quality requirements.

Mark Gibson

Mark Gibson

Regional MD North East and Yorkshire, Sir Robert McAlpine.